Building a new house, opening a shop or moving into a property with no meter all start with the same step: applying for an IESCO new connection. The process has become largely digital. You apply, IESCO surveys the site, you pay a demand notice, and a meter is installed. Most delays come from missing documents, unclear fees or applying through the wrong channel, and all three are easy to avoid once you know them.
This guide walks you through the whole journey for Islamabad, Rawalpindi, Attock, Jhelum and Chakwal, from application to meter installation. It covers where IESCO currently accepts applications, the documents you need, and the difference between single phase and three phase connections. It also explains how the demand notice and security deposit work, and how long NEPRA’s rules give IESCO to install your meter after you pay, with practical tips at each stage.
How the IESCO New Connection Process Works
Before you start filling in forms, it helps to see the full path and the channel IESCO now uses.
The Process at a Glance
- Apply with your details, connection type and required load.
- Submit documents, including CNIC, ownership proof and the wiring test report.
- Site survey: IESCO staff visit the premises and assess what is needed.
- Demand notice: IESCO issues a demand notice listing the charges.
- Pay the demand notice and upload or submit the paid copy.
- Installation: IESCO installs and energises the meter.
Which Portal or App to Use in 2026
Many older guides tell you to apply on enc.com.pk. That main ENC portal now shows a notice saying IESCO consumers should use iesco.enc.com.pk. When we checked the IESCO ENC portal, its menu offered Track, Print Form, Print DN, Pay DN and Upload DN, and it asked applicants to use the Power Smart or IESCO Smart app and eOps, or to visit their nearest Customer Facilitation Center. In short, you apply through the app or a facilitation center, and use the IESCO ENC portal to follow and pay your case.
IESCO New Connection Online Apply: Step by Step
The exact screens may change as IESCO updates its systems, so follow the labels in the app or at the counter.
Applying Through the IESCO Smart or Power Smart App
IESCO Smart is a PITC app whose store listing says it handles services including new connection, change of attributes and meter change requests. To make your IESCO online application for new connection:
- Install IESCO Smart or Power Smart from the official app store and create your profile.
- Open the new connection service and choose IESCO.
- Select the connection category (domestic, commercial and so on) and the load you need.
- Fill in the applicant, address and contact details carefully.
- Attach scans or clear photos of the required documents.
- Submit and save the tracking or application ID shown.
Applying at a Customer Facilitation Center
If you prefer help in person, visit your nearest IESCO Customer Facilitation Center with original documents and copies. Staff can enter the application for you and give you a tracking ID. This is a good option if your documents are unusual, such as an inheritance case or a property with separate portions.
Commercial Applications in Islamabad
The IESCO ENC portal states that all commercial applications for Division Islamabad-I must be made only through the Business Facilitation Center (BFC) in G-7/2, near Sitara Market, Islamabad. If you are applying for a shop or office in that division, go there directly instead of applying elsewhere.
Information on the Application Form
The IESCO new connection application form asks for details such as:
- Applicant’s name, father’s or husband’s name and CNIC number
- Full site address and a nearby landmark
- Mobile number and email address
- Connection type and category (domestic, commercial, etc.)
- Required sanctioned load in kW
- Reference number of a nearby existing connection, if asked
Once submitted, you can use Print Form on iesco.enc.com.pk to download a copy of your application.
Documents Required for an IESCO New Meter Connection
Incomplete documents are the most common reason applications stall. NEPRA’s Consumer Service Manual (CSM) sets the basic requirements.
Core Documents
| Document | Why it is needed |
|---|---|
| CNIC copy of the applicant | To identify the applicant |
| Ownership proof of the premises | The CSM (clause 2.3.1) makes ownership proof mandatory for a new connection |
| Approved map, site plan, layout plan or NOC from the civic agency | Required under the CSM (clause 2.3.6), depending on the area |
| Wiring test report | Confirms the internal wiring is safe |
Ownership proof can include a registry, transfer letter, allotment letter or similar property document. Ask your facilitation center which one fits your case. Keep originals ready, as the CSM-based process allows IESCO staff to collect hard copies at the site survey.
Wiring Test Report
The wiring test report is issued by a licensed wiring contractor after checking your internal wiring. According to NEPRA, the CSM requires this report to be submitted along with the application form, and a missing report can delay installation. IESCO publishes a list of approved Test Report Contractors on its website. Get the report only after your wiring, earthing and distribution board are complete.
Tenants and Separate Portions
- Tenants: expect to provide a No Objection Certificate (NOC) from the owner along with the ownership proof. NEPRA’s 2023 proposed CSM amendments include this requirement for tenants, so confirm the current rule at your facilitation center.
- Separate portions: under the CSM, a premises needs a separate entrance, kitchen and electric circuit for each portion to get more than one connection.
Single Phase vs Three Phase Connection
The phase you need depends on how much electricity your property will use. IESCO confirms the final load and connection type during the survey.
| Single phase | Three phase | |
|---|---|---|
| Typical use | Small homes and shops with basic appliances | Larger homes, several ACs, water pumps, businesses |
| Example load (Ministry of Energy) | 3 kW | 5 kW |
| Material cost (example) | Lower | Higher |
| Billing | Usually normal unit slabs | At 5 kW and above, residential tariff is Time of Use |
Choosing Your Sanctioned Load
Your sanctioned load is the maximum load you are approved to use, in kW. Add up your main appliances, such as ACs, a water pump, an electric geyser and an iron, and leave some room for future use. Do not ask for far more than you need. A higher load can mean a three phase connection, a higher security deposit and, at 5 kW or more, Time of Use billing with higher peak rates. See our IESCO tariff guide to compare categories.
IESCO New Connection Fee, Security Deposit and Demand Notice
There is no single fixed IESCO new connection fee for every applicant. What you pay is set in your demand notice after the survey.
What You Pay For
The demand notice usually covers two main parts:
- Material cost: the meter, cable and any other materials, which depend on your load and the distance from the nearest pole.
- Security deposit: a deposit based on the load and whether the area is urban or rural.
If you are looking for the new connection fee for single phase or three phase, the Ministry of Energy (Power Division) gives this worked example for a house 80 metres from the nearest pole:
| Connection | Material cost | Security deposit (urban) | Security deposit (rural) |
|---|---|---|---|
| Single phase, 3 kW | Rs. 4,000 up to 40 m, plus Rs. 200 per metre from 40–100 m (Rs. 12,000 for 80 m) | Rs. 3,660 | Rs. 1,830 |
| Three phase, 5 kW | Rs. 15,000 up to 40 m, plus Rs. 260 per metre from 40–100 m (Rs. 25,400 for 80 m) | Rs. 6,100 | Rs. 3,050 |
Note that Rs. 6,100 (urban) and Rs. 3,050 (rural) are the security deposits in this example for a three phase 5 kW connection, not for single phase. These are official examples, not a fixed 2026 price list. Your actual IESCO new meter connection fees 2026 will be the amounts printed on your own demand notice.
Paying and Uploading the Demand Notice
- Open Print DN on iesco.enc.com.pk and print your demand notice using your tracking ID.
- Pay it using the Pay DN option or at a bank, as allowed on the notice, before its expiry date.
- Use Upload DN to submit a copy of the paid demand notice, or hand it over at the facilitation center.
- Keep the paid receipt safely. It starts the installation clock.
NEPRA’s decisions confirm that once a demand notice is paid in full, the DISCO generally cannot raise extra charges for material price increases that happen after its own installation deadline has passed.
Site Survey, Verification and Meter Installation
After you apply, the case moves to IESCO’s field staff.
Site Survey and Verification
IESCO staff visit the site to check the address, the distance from the nearest pole or transformer, the requested load and your documents. The Ministry of Energy notes that the company representative can collect hard copies of documents during the survey. Make sure someone is present with originals and that your phone is on. A locked site or wrong address is a common reason for delay. You can follow progress with Track on the IESCO ENC portal.
How Long It Takes After Payment
Under NEPRA’s Performance Standards (Distribution) Rules 2005 read with the Consumer Service Manual, distribution companies must provide the connection within:
- 20 days after payment of the demand notice for loads up to 15 kW
- 34 days after payment for loads above 15 kW and up to 70 kW
If IESCO misses the deadline, contact your subdivision office first. Then register a complaint on 118 using our IESCO complaint guide, and escalate to NEPRA if needed. After the meter is installed, your first bill will show your new reference number. You can then check it any time with our IESCO bill checker.
Frequently Asked Questions
How can I apply for an IESCO new connection online?
Use the IESCO Smart or Power Smart app, or visit a Customer Facilitation Center. Then track your case and print, pay and upload your demand notice on iesco.enc.com.pk.
What is the IESCO new connection fee in 2026?
There is no single fixed fee. Your demand notice lists the material cost and security deposit based on your load, phase, distance from the pole and whether the area is urban or rural.
What documents are required for an IESCO new meter connection?
A CNIC copy, ownership proof, an approved map or NOC where required, and a wiring test report. Tenants also need the owner’s NOC.
How much is the security deposit for a single phase connection?
In the Ministry of Energy’s example, a single phase 3 kW connection has a security deposit of Rs. 3,660 in urban areas and Rs. 1,830 in rural areas. Your demand notice shows your actual amount.
How long does it take to get a new IESCO electricity connection?
NEPRA’s rules require installation within 20 days of paying the demand notice for loads up to 15 kW, and within 34 days for 15–70 kW. Time before the demand notice depends on survey and document checks.
Conclusion
Getting an IESCO new connection is straightforward when you follow the current channel and prepare your papers early. Apply through the IESCO Smart or Power Smart app or a Customer Facilitation Center. Keep your CNIC, ownership proof and wiring test report ready. Pay the demand notice on iesco.enc.com.pk. Fees depend on your load, phase and distance from the pole, so check your demand notice carefully, keep the receipt, and hold IESCO to NEPRA’s installation deadline if the meter is not installed on time.